The city overpaid almost $6 million to turn a Throgs Neck landfill into a golf course, but the job was never completed, according to a

THROGS NECK - The city overpaid almost $6 million to turn a Throgs Neck landfill into a golf course, but the job was never completed, according to a report.

City Comptroller William Thompson Jr.'s office recently released an audit of the Department of Parks and Recreation's Ferry Point Park project. Thompson found the department wasted millions in its dealings with Ferry Point Partners, which was supposed to build the golf course.

The developer was supposed to clear the land. The company also undertook the job of clearing toxic levels of methane gas that were found in the area in 1999.

In the report, the comptroller recommends the department ensure city funding is only used for authorized purposes. He also wants the agency to better track the progress of its projects.

The Parks Department, which denounces the report, says the price ballooned because of the methane gas and other toxins found at the site. However, the department terminated its contract with Ferry Point Partners in November 2006.

The golf course was supposed to have opened in 2001.

advertisement | advertise on News 12

Trending Video

VIDEO: Scenes from fatal accident 1 VIDEO: Scenes from fatal accident
Two brothers died after their car drifted off 2 The Buzz: Brothers die in Bronx crash
3 Neighborhood Brief for Feb. 19
At least 20 cars were damaged when the 4 2nd-floor parking garage collapses on Jerome Avenue
Fire officials say the parking garage on Jerome 5 2nd-floor garage collapses on Jerome Avenue

advertisement | advertise on News 12

Features

Sorry to interrupt...

Your first 5 are free

Access to News12 is free for Optimum, Comcast®, Time Warner® and Service Electric℠ video customers.

Please enjoy 5 complimentary views to articles, photos, and videos during the next 30 days.

LOGIN SUBSCRIBE